Major Maintenance Works

(Updated 14th May 2008)

 Planned Major Works 2007

Building/Area

Works

Start Date

Completion Date

Lionel Robbins Building - Library

Expansion of course collection and creating additional study spaces

Summer vacation - 2007

To be agreed

 

Expansion of rare book archive storage

Late 2007

To be agreed

Towers 1, 2, & 3

Major refurbishment of lifts - two lifts in each Tower will remain in operation.  Tower 1 is now completed, Tower 2 is currently being refurbished.  Work on Tower 3 will start in early September 08

17 Mar 08

End of February 2009

Library Scenic Lifts

Controller refurbishment

Summer 08

TBC

 

 

^